Plainfield Updates: Road work & More

Bridge Project

Work on the Renwick Road Bridge Project is moving along as scheduled.  Accurate Steel has been on site completing rebar installation for the Pier 4 pier cap.  All Pier 4 rebar and form work has been inspected and found acceptable. Albin Carlson has poured Pier 4 and has continued cofferdam excavation and clean up.  Albin Carlson has also been working on the layout for the temporary widening of Renwick Road.  Albin Carlson has also been driving piling at the west side river abutment.  The east abutment has been excavated, and encasement and mud slab work have been completed.  Valor Technologies was on site removing the asbestos from houses one (1) and seven (7).  Len Cox and Sons was on site installing storm sewer truck lines on the west side of the river.  They also have placed the storm sewer lateral runs at the various stations.

 

Again, there have been no major construction delays, and the project is still earmarked for completion by November, 2012.

 

 

Mowing

 

With the good weather, we have started our regular mowing cycles.  Mowing has taken place on County Line Road, Taylor Road (143rd St.), Renwick  Road, and all the area within and by the new bridge.

 

Storm Damage and Tree Trimming

 

Several days of high winds have created some damage to trees.  Two-man crews were dispatched to cover the entire Road District to pick up downed branches and trim several trees.

 

Pot Hole Patching

 

One two-man crew has been doing additional work hot-patching pot holes with blacktop where needed.

 

Garbage/Trash Pickup

 

All Township Highway Department roads were traveled, and several bags of trash and garbage were picked up in April.

 

Shoulder Gravel

 

New shoulder gravel was installed by Highway Department personnel in several of the township subdivisions.

 

Ditching and Culvert Replacement

 

New ditch and culvert work started on Friday, April 27, in the Williamsburg Subdivision.  This new project will take around two weeks to complete.  After the completion of this project, the next one will take place in July.

 

Clean Catch Basins

 

The weather has provided the Highway Department crew the opportunity to keep all curbs and catch basins clean on a regular basis.

 

Branch Pick-up

 

The branch pick-up program started on Monday, April 2.  Two man crews have been covering the entire Road District picking up branches on each Monday.  This program will continue through the last Monday in October.

 

Park District Bike Path

 

There have been no new developments regarding a possible bike path funded by the Plainfield Park District crossing from the west side of the Du Page River to the east side nears the new and old bridges.

 

Thank you

 

The Plainfield Township Highway Department would like to extend a sincere thank you to every resident of Plainfield Township for your continued support.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s